This project involved the maintenance dredging to restore navigation depths in specified areas of the Port of Belfast. The four main areas of the port are: Area 1 – Central, Area – 2 Herdman Channel, Area 3 – Musgrave Channel, Area 4 – Turning circle, Victoria Channel and Approach Channel.

Trailing suction hopper dredgers, Crestway and Medway worked together tom complte ethe dredging works. A contract duration of twelve weeks was permitted, however the works were complete in four.